Monday 1 December 2008

Farnborough Town Centre Schedule update



There are 6 phases in the above plan. Phase 1 and 2 are now complete. Phase 4 is the major work currently being carried out now, building the superstore units and Hotel, which are blocks one and two. According to the new schedule, these will be completed November 2009. The remaining work phase 5 and 6 in the map above and units 3 and 4 in the schedule below are the works to be completed adjacent to the main site.
The final piece of the puzzle is the Cinema construction, which is now expected to start in the summer of 2009 and completed October 2010.